Bunker: Except as otherwise provided, a mandatory Bunker Fuel Surcharge will be assessed on all shipments in addition to all other rates and charges published herein as follows:
A. Bunker Surcharge Application Between Canada and the British Virgin Island Ports, Dominican Republic Ports, Windward Island Ports, Leeward Island Ports or South America Ports; or Between British Virgin Island Ports, Bahamas Ports, Dominican Republic Ports, Turks & Caicos Ports, Cayman Island Ports, Windward Island Ports, Leeward Island Ports or South America Ports; The bunker surcharge between shall be based on the following:
|
Equipment Size |
Current Bunker Surcharge |
Bunker Surcharge Effective 01/01/2012 (C, A, I) |
Bunker Surcharge Effective 01/15/2012 (C, A, I) |
Bunker Surcharge Effective 01/29/2012 (C, A, I) |
Bunker Surcharge Effective 02/12/2012 (C, A, I) |
|
20' Equipment |
$390.00 | $780.00 | $810.00 | $840.00 | $870.00 |
|
40' Equipment |
$780.00 | $1,560.00 | $1,620.00 | $1680.00 | $1740.00 |
|
Greater than 40' Equipment |
$878.00 | $1,755.00 | $1,823.00 | $1890.00 | $1958.00 |
|
Vehicles not exceeding 700 CFT |
$228.00 | $455.00 | $473.00 | $490.0 | $508.00 |
|
Vehicles Exceeding 700 CFT Breakbulk W/M (ST/FT) |
$18.35 | $36.71 | $38.12 | $39.53 | $40.94 |
|
CWT for LCL - 100 LBS |
$0.92 | $1.84 | $1.91 | $1.98 | $2.05 |
|
CFT for LCL - 1 CFT |
$0.46 | $0.92 | $0.95 | $0.99 | $1.02 |
|
Barrel - Each |
$7.20 | $13.73 | $14.26 | $14.78 | $15.31 |
|
Pallet - Each |
$35.45 | $70.91 | $73.64 | $76.36 | $79.09 |
B. Bunker Surcharge Application Between Canada and the Bahamas Ports : The bunker surcharge shall be based on the following:
|
Equipment Size |
Current Bunker Surcharge |
Bunker Surcharge Effective 01/01/2012 (C, A, I) |
Bunker Surcharge Effective 01/15/2012 (C, A, I) |
Bunker Surcharge Effective 01/29/2012 (C, A, I) |
Bunker Surcharge Effective 02/12/2012 (C, A, I) |
|
20' Equipment |
$195.00 | $390.00 | $405.00 | $420.00 | $435.00 |
|
40' Equipment |
$390.00 | $780.00 | $810.00 | $840.00 | $870.00 |
|
Greater than 40' Equipment |
$439.00 | $878.00 | $911.00 | $945.00 | $979.00 |
|
Vehicles not exceeding 700 CFT |
$114.00 | $228.00 | $236.00 | $245.00 | $254.00 |
|
Vehicles Exceeding 700 CFT Breakbulk W/M (ST/FT) |
$9.18 | $18.35 | $19.06 | $19.76 | $20.74 |
|
CWT for LCL - 100 LBS |
$0.46 | $0.92 | $0.95 | $0.99 | $1.02 |
|
CFT for LCL - 1 CFT |
$0.23 | $0.46 | $0.48 | $0.49 | $0.51 |
|
Barrel - Each |
$3.60 | $6.86 | $7.13 | $7.39 | $7.66 |
|
Pallet - Each |
$17.73 | $35.45 | $36.82 | $38.18 | $39.55 |
C. Bunker Surcharge Application Between Canada and Turks & Caicos or Cayman Island Ports: The bunker surcharge shall be based on the following:
|
Equipment Size |
Current Bunker Surcharge |
Bunker Surcharge Effective 01/01/2012 (C, A, I) |
Bunker Surcharge Effective 01/15/2012 (C, A, I) |
Bunker Surcharge Effective 01/29/2012 (C, A, I) |
Bunker Surcharge Effective 02/12/2012 (C, A, I) |
|
20' Equipment |
$230.00 | $520.00 | $540.00 | $560.00 | $580.00 |
|
40' Equipment |
$460.00 | $1040.00 | $1080.00 | $1120.00 | $1160.00 |
|
Greater than 40' Equipment |
$517.00 | $1170.00 | $1215.00 | $1260.00 | $1305.00 |
|
Vehicles not exceeding 700 CFT |
$134.00 | $303.00 | $315.00 | $327.00 | $338.00 |
|
Vehicles Exceeding 700 CFT Breakbulk W/M (ST/FT) |
$10.83 | $24.47 | $25.41 | $26.35 | $27.29 |
|
CWT for LCL - 100 LBS |
$0.54 | $1.22 | $1.27 | $1.32 | $1.36 |
|
CFT for LCL - 1 CFT |
$0.27 | $0.61 | $0.64 | $0.66 | $0.68 |
|
Barrel - Each |
$4.22 | $9.15 | $9.50 | $9.86 | $10.21 |
|
Pallet - Each |
$20.91 | $47.27 | $49.09 | $50.91 | $52.73 |
D. Bunker Surcharge Application Between Canada and Venezuela, Mexico, Jamaica, Aruba, Curacao: The bunker surcharge shall be based on the following:
|
Equipment Size |
Current Bunker Surcharge |
Bunker Surcharge Effective 01/01/2012 (C, A, I) |
Bunker Surcharge Effective 01/15/2012 (C, A, I) |
Bunker Surcharge Effective 01/29/2012 (C, A, I) |
Bunker Surcharge Effective 02/12/2012 (C, A, I) |
|
20' Equipment |
$390.00 | $780.00 | $810.00 | $840.00 | $870.00 |
|
40' Equipment |
$780.00 | $1,560.00 | $1,620.00 | $1680.00 | $1740.00 |
E. Bunker Surcharge Application Between Canada and All Ports not otherwise listed
|
Equipment Size |
Current Bunker Surcharge |
|
20' Equipment |
$1000.00 |
|
40' Equipment |
$2000.00 |
|
LTL - W/M (ST/FT) |
$100.00 |